Regulator AERA on Friday steeply slashed the user development fee at the Bengaluru international airport to ₹300 for domestic and ₹997 for international passengers for the five-year control period till March 2031.
For the first time, the watchdog implemented the incremental ARR (Average Revenue Requirement) framework wherein the cost borne by the Bengaluru airport operator can be recovered from the passengers only after completing the high-value capex projects.
Previously, the User Development Fee (UDF) was recovered from the flyers before project completion.
UDF for departing domestic passengers has been fixed at ₹300 per passenger, lower than the existing amount of ₹550 and also lower than ₹450 proposed by the airport operator BIAL, Airports Economic Regulatory Authority of India (AERA) said on Friday.
"Similarly, UDF for departing international passengers has been fixed at ₹997 per passenger, as against ₹1,215 proposed by the airport operator and the existing UDF ₹1,500.
"Further, the landing charges have also been rationalised and determined at ₹442 per MT (Metric Tonne) for domestic flights and ₹652 per MT for international flights for the control period," it said in a release.
Domestic passengers account for around 84% of the total passenger traffic at the Bengaluru airport.
While the fourth control period is from April 1, 2026 to March 31, 2031, the revised UDF amounts will be levied from September 1, 2026.
Advertisement
UDF will be ₹125 and ₹426 for the disembarking domestic and international passengers, respectively at the airport which is operated by the Bangalore International Airport Ltd (BIAL).
Regarding the incremental ARR, the regulator said the approach is intended to ensure that tariff recovery is more closely aligned with the actual availability and use of the said capex projects of the airport and thus protect the airport users from premature tariff for assets that are not yet operational.
"This is also aimed at encouraging the airport operator for timely execution and commissioning of big capex projects at the airport and thus reduce the risk of over-recovery for passengers and airlines in case of delays, deferment, non-execution of such planned capex projects," it noted.
Advertisement
Under the incremental ARR framework, the cost of these identified high capex projects does not get loaded in the airport tariff from the 1st year of the 5-year control period but would instead be recovered through an incremental tariff from the date the respective assets are completed, commissioned and put to use for the airport users.
While the airport operator BIAL proposed a baseline ARR of ₹41,398.93 crore (₹35,252.08 crore in present value terms) for the fourth control period, AERA considered a baseline ARR of ₹14,604.31 crore (₹11,751.55 crore in present value terms).
"This translates into a baseline Yield per Passenger (YPP) of ₹390.42 per passenger, which has been suitably apportioned between landing and parking charges, UDF and other airport charges," the release said.
For the airport, AERA adopted the incremental ARR approach for identified high-value projects, including the ECT, T2 Phase 2 Terminal and T2 Phase 2 Apron, coming only in the fourth year, 2029-30.
"Accordingly, incremental tariff recovery will commence only after the respective assets are completed, commissioned and put to use, thereby aligning tariff recovery with the actual availability of infrastructure to users.
"Thus, the UDF for BIAL for the 4th control period (2026-31) has been kept at a nominal ₹300 per departing domestic passenger. Domestic passengers account for around 84% of the total passenger traffic at Bengaluru airport. This will make air travel affordable to domestic passengers, while supporting the growth of domestic aviation," the release said.