SECI, NTPC, NHPC, SJVN and state agencies can grant eligible renewable projects up to four months of additional time.
Developers have faced procurement and cost pressures for critical materials such as copper and aluminium amid the West Asia crisis.
The Centre has asked the power ministry and Central Transmission Utility to consider corresponding relief on connectivity obligations and financial penalties during the extended period.