Adani Energy Solutions has won an interstate transmission project worth around ₹8,500 crore in Andhra Pradesh under the Centre's Tariff-Based Competitive Bidding (TBCB) mechanism.
The project will provide transmission infrastructure for an estimated 4,500 MW of power demand from upcoming green hydrogen and green ammonia plants in the Vizag region.
Scheduled for completion in 30 months, the project will add 1,582 circuit kilometres of transmission lines and 10,500 MVA of transformation capacity.