Adani estimates construction costs at ₹70-75 crore per MW, putting the initial 400 MW phase at up to ₹30,000 crore.
AdaniConneX is executing the first 400 MW phase of the broader 1 GW data centre project in Visakhapatnam, with initial capacity targeted to go live within 2.5 years.
The project is expected to use 70-80% debt financing, with seven-year debt backed by service contracts providing around 10 years of revenue visibility.